Draper City Basement Finishing Permit: Fee, Plans and Inspections

How to get a basement finishing permit from Draper City: the $100 application fee, the online portal, what the plans must show and how inspections work.

Last reviewed November 2026

$100.00. That is Draper City's application fee for a basement finish permit (Draper City basement submittal sheet). It is invoiced 24 to 48 hours after you submit, and it must be paid before plan review starts. The remaining permit fees vary by project. This page covers what Draper City's Building Division asks for, in the order you meet it. Corner Canyon Basements is a referral service that connects Draper homeowners with licensed local contractors, and it does not issue or process permits.

Rules and fees change. For anything on this page, confirm with the Draper City Building Office at (801) 576-6399 before you submit.

Does a Draper basement finish need a permit?

Yes. Draper City requires a building permit for home work such as basement finishes, remodeling and adding a second kitchen (Draper City). As background, the 2021 International Residential Code as adopted in Utah requires anyone who intends to alter a building, or to install or alter an electrical, gas, mechanical or plumbing system, to apply to the building official and get the permit first (R105.1 on UpCodes, a third-party copy of the code).

Skipping a permit can surface at sale or with an insurer.

Who handles it

Draper City's Building Division reviews plans, issues building permits and does field inspections of buildings (Draper City). The Building Office number is (801) 576-6399. Ask your contractor who pulls the permit. The city's page speaks of "the homeowner/contractor" applying, so both are possible.

The steps

  1. Create an account. Applications go through the city's online services portal, and you create an account to use it (Draper City, building permits).
  2. Prepare the plans. The basement submittal sheet lists what to show (below).
  3. Unlock the files. Digital plan files must be unlocked so city plans examiners can comment. Locked files are returned unreviewed.
  4. Submit. The application goes in through the portal.
  5. Pay the $100. Watch for the invoice, which comes 24 to 48 hours after submission; plan review does not start until it is paid.
  6. Plan review. Ask the Building Office what review time to expect when you submit.
  7. Inspections. You look up building inspections through the same portal.

What the plans must show

From Draper City's basement submittal sheet (PDF):

  • Designed to the currently adopted, applicable codes: the IRC, IBC and NEC.
  • A cross-section with ceiling, fur-down and soffit heights. Surface-mounted lighting cannot encroach into the required minimum height of 7 feet.
  • Emergency egress from bedrooms and from the basement areas the project affects.

Ask the Building Office for the current version of the sheet before you rely on this list.

Which codes

Utah's state construction code, which applies to remodeling statewide, adopts the 2021 International Residential Code and the 2023 National Electrical Code (Utah Code 15A-2-103, version in force from 2026-07-01). Utah's amendments to the IRC are in Utah Code 15A-3-202 (Utah Code 15A-3-202). The code sets these requirements, among others:

SubjectRequirementPage
Ceiling7 feet minimum in habitable spaceFull finish
Escape openingOne in the basement, and one in each basement bedroomEgress windows
Smoke alarmsEach bedroom, outside sleeping areas, each storyBedrooms
Carbon monoxide alarmsEach level and outside sleeping areasBedrooms
Stairs8 inch riser maximum, 9 inch tread minimumFull finish

Radon test before you finish

Test for radon first, whatever the permit asks. The EPA says to test before a remodel starts, because the fix is usually easier and cheaper before the basement is finished (EPA). Utah's Department of Environmental Quality says 1 in 3 Utah homes have elevated radon (Utah DEQ). Whether a radon test is part of Draper's permit is a question for the Building Office.

A basement apartment is a second permit

An owner who adds an internal accessory dwelling unit must get an ADU permit from Draper City, on top of the building permit (Draper City). The basement apartment page has the owner-occupancy, 30-day and lot-size rules.

Common questions

Who pays the $100?

The city sends the invoice after you submit. Whether the contractor or the homeowner pays it is a line in the contract. See the cost page.

How long does review take?

The Building Office can tell you, at (801) 576-6399.

Can you follow the inspections online?

Yes. Building inspections are looked up through the city's online services portal.

Is a permit needed to replace flooring only?

That is a question for the Building Office. The rules above are for basement finishes.

Where these rules come from

The fee, plan and portal details are from Draper City's basement submittal sheet and building permits page, read in November 2026.